Here is how to change project work time schedule in asana
- First click on a project item in the left sidebar Projects menu
- Then click on "Customize" button in the top-right corner of the project page
- Next click on "Project settings" option in the right sidebar settings menu
- Then click on the toggle switch next to "Choose work hours" in the Work schedule section
- Next click on the timezone dropdown field to select the timezone
- Then select the desired timezone from the timezone dropdown list
- Next click on the start time field showing "09:00"
- Then select the desired time as the new start time from the time picker menu
- Next click on the end time field showing "17:00"
- Finally select the desired time as the new end time from the time picker menu